Lower Mount Bethel Township, Northampton County
Lower Mount Bethel Tech Center
Under review A municipal body is actively reviewing it now.
Status basis: A revised map amendment application seeking to rezone about 239 acres to industrial use was filed after an April 2026 town hall and community feedback. We could not confirm the current hearing calendar. On September 14, 2026 the Board of Supervisors voted unanimously to adopt Ordinance 2026-01, the township's data center ordinance, with rules on water, electricity and land use that any data center applicant must meet. That ordinance sets the rules. It is not an approval of this project.
This record reviewed October 3, 2026. Status can change at a single meeting, so check the municipality's own notice before relying on it.
The facts
| Developer | Peron Development and J.G. Petrucci Co. |
|---|---|
| Applicant | Peron Development and J.G. Petrucci Co. |
| Landowner | Could not confirm |
| Where | About 450 acres at Gravel Hill Road and Martins Creek Belvidere Highway, next to the Talen owned Martins Creek and Lower Mount Bethel power plants. The revised plan keeps the campus south of the highway, near Depues Ferry Road. |
| Municipality | Lower Mount Bethel Township, Northampton County |
| Buildings | Could not confirm |
| Size | Could not confirm |
| Land | About 450 originally. The rezoning request covers about 239 acres. We could not reconcile the two figures. acres |
| Power | 1.2 gigawatts, which is 1,200 MW, as presented by the developers. That is larger than Project Atlas. The site sits beside two existing Talen power plants, which the developers give as the reason for the location. |
| Utility | Could not confirm |
| Cooling | Could not confirm |
What the developer says
These figures come from Peron Development and J.G. Petrucci Co., at an April 2026 town hall. We have not seen them independently verified.
- Investment: More than $5 billion
- Jobs: About 500 full time jobs, plus hundreds of construction jobs
- Taxes: $7 million to $8 million a year for the township, against current township revenue of about $550,000. This figure was given as an estimate at a public town hall, not as a formal projection.
- Timeline: Five to seven years to become operational
What we could not find
- The end user. The developers said the project has no identified end user and the building configuration is undefined.
- Cooling type and water source.
- The current review body and hearing date.
- Whether the 450 acre site and the 239 acre rezoning request describe the same ground.
Who is organized
Opposing: An organized resident campaign. A petition against the project has drawn thousands of signatures, and we are citing the count only where a source states it.. Supporting: None we could identify beyond the developer.
How it got here
Decision deadline: Could not confirm.
Latest reporting, not verified by us
Found by an automated daily search. We have not checked these articles and we do not endorse them. Nothing here changes a project's status on this site. A status moves only after a person reads the source.
Sources
- PressLower Mount Bethel Twp. passes ordinance setting guardrails for data centers · WFMZ · September 14, 2026
- PressVote clearing way for major data center shelved as hundreds pack hearing in Slate Belt · lehighvalleylive.com (via Yahoo News) · August 18, 2026
- Press'We will fight until the end': Lower Mt. Bethel residents pack data center town hall | Slate Belt Area | wfmz.com · WFMZ · April 9, 2026
- PressLower Mount Bethel Township data center proposal revised with community feedback, developers say · WFMZ
- Press'We will fight until the end': Lower Mt. Bethel residents pack data center town hall | Slate Belt Area | wfmz.com · WFMZ
The grid and the water right now
Live, the grid this would plug into
checking MWh
Electricity demand right now across PJM, the grid operator for 13 states including Pennsylvania.
Source: U.S. Energy Information Administration, hourly grid monitor. We use EIA rather than PJM's own feed because PJM does not permit republishing its data without a paid membership.
Live, the creeks nearest the site
- checking
Streamflow in cubic feet per second.
Source: U.S. Geological Survey. A gauge reading does not measure anyone's water use. It is the public baseline, so a claim about the water here can be checked against it over time.