South Whitehall Township, Lehigh County
Project Atlas
Under review A municipal body is actively reviewing it now.
Status basis: The Planning Commission met in special session on September 23, 2026 at Parkland High School and ended without a decision, taking the proposal under advisement. Lehigh Valley Press (October 2) reports the commission voted to take the matter under advisement rather than recommend approval or denial, with Chairman David Wilson saying hundreds of pages of review comments remain unresolved. The applicant's attorney told the commission the company was not requesting approval that night and would return with a revised plan at a future date. WFMZ (September 23) and The Morning Call (September 24) both report that the deadline for a decision moved from October 31 to December 31, 2026. We have not yet seen a township document confirming the new date. The Planning Commission only recommends. The Board of Commissioners holds the land use decision. The township engineer told the commission on July 9 that staff could not recommend preliminary approval, and the zoning officer's review recommends denial for non-compliance. Sources: https://www.lvpnews.com/20261002/south-whitehall-planning-commission-takes-project-atlas-under-advisement/ and https://www.wfmz.com/news/area/lehighvalley/lehigh-county/allentown-area/project-atlas-meeting-ends-without-decision-pushing-proposal-back-2-months/article_098ff206-7c3e-483f-91b7-3765daaad2a6.html and https://www.mcall.com/2026/09/24/jarrett-coleman-mark-pinsley-oppose-project-atlas-data-center-south-whitehall/
This record reviewed October 3, 2026. Status can change at a single meeting, so check the municipality's own notice before relying on it.
Next public meeting
Not yet scheduled
South Whitehall Township Planning Commission. No further meeting on Project Atlas has been scheduled. WFMZ reported on September 23 that the township says the next meeting will be publicized as soon as it is scheduled. Check the township's own notices.
The facts
| Developer | Edged US |
|---|---|
| Applicant | CDE Acquisitions, LLC |
| Landowner | Jeras Corporation, per earlier reporting. We could not confirm the landowner of record for every parcel. |
| Where | 410 acres at 2493, 2807 and 2747 North Cedar Crest Boulevard, a consolidation of three parcels owned by the Jeras Corporation, across from Parkland High School |
| Municipality | South Whitehall Township, Lehigh County |
| Buildings | 3 data center buildings of about 492,285 square feet each, a 40,680 square foot accessory building, an electrical substation, a cell tower, 267 parking spaces and three stormwater ponds |
| Size | 1,556,702 total, revised down from 5,038,100 in the December submission |
| Land | 410 acres |
| Power | 725 MW is the figure carried in press coverage of the township's June 2026 review. We have not been able to tie it to an accessible township, PPL, PJM, Public Utility Commission or applicant document that says what kind of number it is: requested capacity, maximum contract demand, full campus buildout, energized load or IT load are all different things and they are not interchangeable. So treat it as reported, not as an established operating load. PPL has separately proposed a new substation north of Hucklebury Road plus three new transmission lines running about 1.5 miles east in a corridor about 250 feet wide to what it calls a new customer facility, subject to Public Utility Commission approval. |
| Utility | PPL Electric |
| Cooling | Closed loop, which the developer says uses no municipal water for daily cooling |
| Distances | Nearest homes more than 1,000 feet from the buildings, Parkland High School almost 1,700 feet, according to the developer |
What the developer says
These figures come from Edged US, on its project site and at public meetings. We have not seen them independently verified.
- Taxes: $16.2 million a year on the developer's own site: $11.5 million to Parkland School District, $2.3 million to South Whitehall Township, $2.4 million to Lehigh County. Some coverage reports $16.5 million. We show both because the sources disagree.
- Jobs: About 250 permanent jobs at $65,000 to $75,000 average, down from 440 in the first plan, plus construction employment
- Water: Saves nearly 2.85 billion gallons a year compared with evaporative cooling. That is a comparison to an alternative, not a measure of what the site would withdraw.
- Noise: Under 54 decibels at the property line
- Investment: A $9 billion construction budget, and about $99.5 million in annual economic impact
- Other: A 160 acre park dedicated for public use
What the officials found
Every public body that has reviewed this, and what each one concluded. not by us and not by anyone campaigning on either side.
South Whitehall Township
Recommends denialZoning officer and director of development Kent Baird's review recommends denial for non-compliance. Reporting places a review in June 2026 and a 62 page review dated September 3, 2026, so ask the township which document is operative. Consultants flagged karst features including closed depressions and surface pits, lighting aimed at homes rather than away in violation of the ordinance, missing documentation on emissions from the backup diesel generators, incomplete PPL substation details, and a warehouse use not permitted as a data center accessory. The planning consultant 4ward Planning called the $9 billion budget and the 725 MW figure not credible at the reduced scale, since neither changed when the project was cut roughly in half.
Lehigh Valley Planning Commission
Could align, with conditionsIn a June 25, 2026 review the LVPC said the revised plan addressed numerous of its comments and has the potential to align with the regional plan if it avoids disturbing sensitive natural resources. It still cited noise, lighting, air quality and visual impacts, and said signals may be needed at the new road because of traffic conflicts with Parkland High School. The project is projected to generate 1,154 weekday vehicle trips.
Parkland School District
Unacceptable as writtenThe district's public position is that the second plan is of high concern, incomplete, and lacks proper safety mitigation strategies, and that in its current form the plan is unacceptable. It notes the high voltage substations remain directly across the street from the high school with no sign of relocation, that the tenant's identity is hidden behind a non-disclosure agreement, and that a power loss would disable security cameras, electronic door locks, fire alarms and emergency lighting. Superintendent Dr. Mark J. Madson submitted concerns to the township, Edged, PPL Electric and the Lehigh County Authority.
Three township advisory panels
Questions, no verdictOn September 9, 2026 WFMZ reported that the landscape and tree commission, the environmental advisory council and the park and recreation board each gave feedback, none of it a final approval or denial. Between them they asked for more detail on the vegetation buffers, questioned why single story buildings could not be built taller on a smaller footprint, asked for continuous noise monitoring through the first year rather than the quarterly monitoring proposed, and said the project's energy use needs further explanation. The plans show about 72 acres of woodland cleared with about 12 acres reforested, and 267 parking spaces.
Parkland School District, on the generators
Count disputed, 356 vs 2,000The district reports the current plan keeps 356 backup diesel generators, upgraded at the district's request from Tier 2 to Tier 4, the strictest EPA tier for non-road engines. At the September 8 public meeting a resident instead described 2,000 diesel generators, and another raised almost 2.5 million gallons of stored petroleum product. We could not find a document that settles the generator count, so we are publishing both figures and neither as fact. The township manager has disputed the applicant's position that generator testing is exempt from the noise rules, saying routine testing counts as normal operation.
What we could not find
- What the 725 MW figure actually measures. Nobody we can find has published a document defining whether it is requested capacity, contract demand, full buildout or energized load. That is the single most important unanswered question about this project and it should be asked in public.
- The end tenant. Parkland School District says the identity is hidden behind a non-disclosure agreement, so nobody in public knows who would run the buildings or what would run in them.
- Whether the 725 MW figure has been independently confirmed by PPL, and how much of it arrives in the first phase.
- Whether the tax projection rests on an assessed value the county has agreed to.
- Whether a formal public hearing will be granted.
- How the separate PIRT district draft ordinance interacts with this review.
- The generator count. The school district says 356. A resident at the September 8 meeting said 2,000. Ask for the number on the plan sheet, with the testing schedule in writing.
Who is organized
Opposing: South Whitehall Civic Alliance, which runs opposeatlasdc.com. Supporting: None we could identify beyond the developer.
How it got here
Decision deadline: December 31, 2026, as reported by WFMZ and The Morning Call after the September 23 meeting, moved from October 31. We have not yet seen a township document confirming it. The Board of Commissioners decides.
Latest reporting, not verified by us
Found by an automated daily search. We have not checked these articles and we do not endorse them. Nothing here changes a project's status on this site. A status moves only after a person reads the source.
Sources
- PressSouth Whitehall Planning Commission takes Project Atlas under advisement | Lehigh Valley Press · Lehigh Valley Press · October 2, 2026
- PressProject Atlas meeting ends without decision; deadline to act on plan pushed to New Year’s Eve · WFMZ · September 23, 2026
- Press‘No one wants you here:’ Pa. state senator, opponent join opposition to South Whitehall data center near high school · The Morning Call · September 24, 2026
- PressAhead of key meeting on South Whitehall data center plans, township identifies long list of concerns · WFMZ · June 9, 2026
- PressLVPC reviews revamped South Whitehall ‘Project Atlas’ data center plan · WFMZ · June 25, 2026
- Press3 South Whitehall panels offer feedback on Project Atlas data campus · WFMZ · September 9, 2026
- PrimaryAtlas Data Center Update/Community FAQ - Parkland School District · Parkland School District
- PressPPL proposes new electric lines, substation near possible S. Whitehall data center site · WFMZ
- PressResidents push for public hearing as South Whitehall takes new look at hyperscale data center · Lehigh Valley Public Media · July 14, 2026
- PressSouth Whitehall schedules special September session at Parkland High School for hyperscale data center proposal · Lehigh Valley Public Media · July 31, 2026
- PressSouth Whitehall Township Data Center Fight Escalates · Hoodline · September 17, 2026
- PrimaryProject Atlas - A Lower-Impact Industrial Use for South Whitehall Township · Edged US (the developer)
- PrimaryOppose Atlas Data Center · South Whitehall Civic Alliance (the opposition group)
Your call
Loading the question
This is a public straw poll, not a scientific survey and not a substitute for the township's own process. One response per browser, no names or emails collected, and you can change your answer.
The grid and the water right now
Live, the grid this would plug into
checking MWh
Electricity demand right now across PJM, the grid operator for 13 states including Pennsylvania.
Source: U.S. Energy Information Administration, hourly grid monitor. We use EIA rather than PJM's own feed because PJM does not permit republishing its data without a paid membership.
Live, the creeks nearest the site
- checking
Streamflow in cubic feet per second.
Source: U.S. Geological Survey. A gauge reading does not measure anyone's water use. It is the public baseline, so a claim about the water here can be checked against it over time.