Upper Macungie Township, Lehigh County

Tek Park expansion

Under construction Ground is broken.

Status basis: TierPoint acquired the campus for $175 million and announced a 100 megawatt expansion including substation work, reported by trade press as due to complete in the second half of the following year. Because it expands a facility that already operates, it never went through a new zoning fight.

This record reviewed October 3, 2026. Status can change at a single meeting, so check the municipality's own notice before relying on it.

The facts

DeveloperTierPoint, LLC
ApplicantTierPoint, LLC
LandownerTierPoint, LLC
Where9999 Hamilton Boulevard, a 137 acre, nine building campus that opened in 1988 as an AT&T optoelectronics headquarters
MunicipalityUpper Macungie Township, Lehigh County
Buildings9 on the campus
SizeExpansion square footage not broken out in the coverage we found
Land137 acres
PowerA 100 MW expansion, including utility substation work. We could not confirm the serving utility from the sources we found.
UtilityCould not confirm
CoolingCoverage refers to advanced cooling for AI and GPU workloads. No cooling type or water figure was published that we could find.

What the developer says

These figures come from TierPoint and trade press. We could not confirm which party originated the jobs figures.. We have not seen them independently verified.

  • Jobs: About 100 new permanent jobs, and an estimated 350 or more construction and engineering jobs
  • Investment: $175 million to acquire the campus

What we could not find

  • Exact construction timeline and completion date.
  • Cooling type and water use.
  • Whether the expansion triggered any township review.

Who is organized

Opposing: None we could identify. Supporting: None we could identify beyond the developer.

How it got here

How Project Atlas got here Amber marks the moments that changed the project.
1988The campus opened as an AT&T optoelectronics headquarters.2026TierPoint acquired the campus and announced a 100 MW expansion.

Decision deadline: Not applicable.

Sources

  1. PressTek Park’s Next Chapter: Lehigh Valley Tech Hub Expanding Under New Ownership · Lehigh Valley Economic Development Corporation
  2. PressTierPoint acquires leased data center site in Pennsylvania, plans 100MW expansion · Data Center Dynamics
  3. PressNew owner plans data center expansion at Tek Park - LVB · Lehigh Valley Business

The grid and the water right now

Live, the grid this would plug into

checking MWh

Electricity demand right now across PJM, the grid operator for 13 states including Pennsylvania.

Source: U.S. Energy Information Administration, hourly grid monitor. We use EIA rather than PJM's own feed because PJM does not permit republishing its data without a paid membership.

Live, the creeks nearest the site

  • checking

Streamflow in cubic feet per second.

Source: U.S. Geological Survey. A gauge reading does not measure anyone's water use. It is the public baseline, so a claim about the water here can be checked against it over time.