PRISM AI Safety Hub

Upper Mount Bethel Township, Northampton County

Slate Belt Tech Campus

Early or informal Discussed publicly but no full application confirmed.

Status basis: Concept stage, and contested. A validity challenge was filed on July 23, 2026. A draft memorandum of understanding would include $50 million in donations at full buildout, which the township solicitor has said is not a binding contract. On August 24, 2026 supervisors voted 3 to 2 against abandoning the MOU talks. On September 21, 2026 they voted 3 to 1 for the township's own data center ordinance, which makes data centers a conditional use in the I-2 and I-3 districts with full hearings before the board, and sent it to the Lehigh Valley Planning Commission for review. A competing ordinance from Slate Belt Holdings that would have made data centers permitted by right died without a second. WFMZ reports the validity challenge is still undecided, and if the court sides with Slate Belt Holdings the developer may not have to follow the new ordinance or parts of it. On September 28 supervisors discussed hiring an outside consultant to negotiate a community benefits agreement and tabled the decision to their next meeting. No land development plan has been filed that we could find.

This record reviewed October 3, 2026. Status can change at a single meeting, so check the municipality's own notice before relying on it.

Next public meeting

Not yet scheduled

Upper Mount Bethel Township Board of Supervisors. The decision on hiring a community benefits negotiator was tabled to the supervisors' next meeting. We have not confirmed that date. Check the township's own notices.

Questions to ask

The facts

DeveloperSlate Belt Holdings, a joint venture of River Pointe Logistics and Talen Energy
ApplicantSlate Belt Holdings
LandownerSlate Belt Holdings, which acquired the land from River Pointe
Where753 acres at an existing industrial park outside Bangor
MunicipalityUpper Mount Bethel Township, Northampton County
BuildingsUp to 23 data center buildings at 201,500 square feet each, plus five substations shown in the rendering
SizeAbout 4,634,500 if all 23 buildings are built
Land753 acres
PowerThe community benefits agreement is written around a goal of 2 gigawatts, which is 2,000 MW. That is a goal in a draft agreement at concept stage, not an approved or applied for load, and it is the largest figure attached to any project in this region.
UtilityCould not confirm
CoolingCould not confirm. Water was listed as a community priority to address, without consumption figures.

What the developer says

These figures come from Slate Belt Holdings, on its own site slatebelttechcampus.com and in the draft agreement. We have not seen them independently verified.

  • Community_Benefits: The draft community benefits agreement pledges $50 million if the campus reaches its 2 gigawatt goal
  • Positioning: The developers say the project is intended to bring significant private investment to an existing industrial park while setting clear, responsible standards for data center development

What we could not find

  • When, or whether, a land development plan gets filed.
  • The end user, and whether the buildings would train or run large AI models.
  • Water source and cooling method.
  • Whether the $50 million pledge survives into a signed agreement, and what triggers it.

Who is organized

Opposing: None we could identify. Supporting: None we could identify beyond the developer.

How it got here

How Project Atlas got here Amber marks the moments that changed the project.
August 2026The memorandum of understanding was revised on August 10, 18 and 25.September 4, 2026The developers unveiled a public website making their case, and WFMZ reported the campus would be 23 buildings on 753 acres.September 21, 2026Supervisors voted 3 to 1 to send the township's own data center ordinance, making data centers a conditional use, to the Lehigh Valley Planning Commission. They rejected the developer's version, which would have made data centers permitted by right.September 28, 2026Supervisors discussed hiring consultant Paul Soult to negotiate a community benefits agreement with Slate Belt Holdings, on a $25,000 retainer plus a 2 percent commission. They tabled it to their next meeting.

Decision deadline: None set. No land development plan has been submitted..

Sources

  1. Press'Keep the power': Upper Mount Bethel votes in favor of data center regulations | Slate Belt Area | wfmz.com · WFMZ · September 22, 2026
  2. PressPa. township mulls hiring outside negotiator for $50M offer from data center developer · lehighvalleylive.com (via Yahoo News) · September 29, 2026
  3. PressMaking their case: Developers unveil website for data center campus with 23 buildings in UMBT · WFMZ · September 4, 2026
  4. PrimarySlate Belt Technology Campus · Slate Belt Holdings (the developer)

The grid and the water right now

Live, the grid this would plug into

checking MWh

Electricity demand right now across PJM, the grid operator for 13 states including Pennsylvania.

Source: U.S. Energy Information Administration, hourly grid monitor. We use EIA rather than PJM's own feed because PJM does not permit republishing its data without a paid membership.

Live, the creeks nearest the site

  • checking

Streamflow in cubic feet per second.

Source: U.S. Geological Survey. A gauge reading does not measure anyone's water use. It is the public baseline, so a claim about the water here can be checked against it over time.