The Data Center Desk
What a data center actually means for your bill, your water and your taxes
The honest version. Every number here is sourced and dated, the projections are labeled as projections, and the things nobody can answer yet are listed instead of filled in.
Figures reviewed September 22, 2026. Each row carries its own source and date.
Put a number on it
How many homes is a megawatt?
Enter a project's megawatts and how hard you think it runs. The arithmetic is shown so you can check it.
checking Pennsylvania homes
One megawatt of continuous load is 1,000 kW running 8,760 hours, which is 8,760,000 kWh a year. Divided by the average Pennsylvania household's 9,804 kWh a year, that is about 894 homes per megawatt of continuous draw. A published megawatt figure is usually the maximum a site is permitted to draw, not its average, so the honest version of this number depends on how hard the buildings actually run. We show the assumption instead of hiding it.
What that looks like
The household comparison is a way to picture the size of the load. It does not mean homes lose power, and a data center pays for the electricity it uses.
What has actually happened to power costs
A capacity price is not a household bill. It is one wholesale component, and it reaches you through your utility's rates, your supplier and your rate class. Anyone converting one straight into the other is skipping several steps.
The numbers that matter, each with its source
Every figure above links to the document it came from. If one of them is wrong, the document will show it.
Both cases, from the same facts
The case for
The strongest honest case for these projects: Pennsylvania's new cost causation rule is designed to make the developer, not the ratepayer, pay for the grid upgrades their load causes. The tax base is real money for districts that need it. Construction employment is real. And in The Dalles, Oregon, a data center's tax contribution is credited with funding an infrastructure upgrade that lowered local household water costs rather than raising them.
The case against
The strongest honest case against: the grid cost attribution from PJM's own monitor is large and rising, and the state's tax exemption is running far ahead of its own projections. On whether promised local revenue actually arrives, we could find no Pennsylvania case tested after the fact. The two comparable cases we could check are both out of state: in Cook County, Illinois, data center owners won assessment reductions of 29% to 68% on appeal, and in Loudoun County, Virginia, the data center tax base came in about $1.1 billion under forecast. Two cases in other states is not a pattern, and we are not going to call it one.
Both of those paragraphs are built from the same sourced facts above. If one of them is wrong, show us the document and we will change it.
What honestly cannot be known yet
- There is no audited figure for what data centers add to a Pennsylvania household's monthly bill. Anyone who gives you one is giving you a projection, and you should ask whose.
- Whether the new large load tariff actually keeps these costs off residential bills. It is too new to have been tested.
- Whether a closed loop cooling claim holds in practice. The design genuinely uses far less water than evaporative cooling, but the way to check it is the actual water withdrawal permit, not the brochure.
- Whether promised tax revenue arrives. We found no Pennsylvania case where a data center's projected school or county tax revenue was checked after the fact against what was promised at approval. In Illinois, data center owners won assessment reductions of 29% to 68% on appeal. In Loudoun County, Virginia, the data center tax base came in about $1.1 billion under forecast. Those are other states, and we label them that way.
Most sites in this argument will give you a confident number here. We would rather tell you which questions are still open, because those are the ones worth asking out loud at a meeting.
Where the utility stands
PPL Electric, the utility for most of the Lehigh Valley, has reported a fast growing queue of data center requests across its whole Pennsylvania territory. Trade coverage through 2026 has put its advanced stage pipeline at figures from 14 GW to 28.3 GW to 31.8 GW at different points in the year, and its broader interconnection queue above 60 GW. These are statewide numbers, not Lehigh Valley numbers, and they change every quarter. We show the range rather than pick the biggest one.
- PressData centers drive PPL's 31.8 GW pipeline as PUC sees industrial power up 51% a year · Lehigh Daily · 2026
- PressMonitoring Analytics - PJM State of the Market - 2026 · Monitoring Analytics, the PJM Independent Market Monitor · 2026
Who has written rules, and who has not
A municipality adopting a data center ordinance and a project winning approval are two different events. These are the rules, by township.
| Municipality | County | Status | Date | What it does |
|---|---|---|---|---|
| Upper Macungie Township | Lehigh | Adopted | December 2025 | Interim amendment making data centers a conditional use in General Industrial and Rural Technology districts, with 200 foot setbacks from homes, schools and places of worship, berms, sound studies, emergency response plans, and a required demonstration of power and water capacity. It does not apply retroactively. source |
| North Whitehall Township | Lehigh | Adopted | March 2026 | Ordinance approved, with supervisors saying they plan to consider further restrictions. source |
| Lowhill Township | Lehigh | Adopted | July 2026 | A 23 page Digital Infrastructure Facility ordinance. Conditional use, and it requires an electrical utility impact study, a water feasibility study, and closed loop cooling. source |
| City of Allentown | Lehigh | Adopted | August 2026 | Council adopted data center zoning 4 to 2, then unanimously added a measure restricting data centers to industrial manufacturing zoned property with an 8 acre minimum lot for facilities over 50,000 square feet. source |
| Lower Macungie Township | Lehigh | In progress | April 2026 | Board advanced a draft modeled on Upper Macungie's, with annual water and electricity usage reporting and noise studies. We could not confirm a final adoption vote. source |
| Whitehall Township | Lehigh | In progress | August 10, 2026 | Commissioners took a first look at a proposed ordinance. Not adopted as far as we can confirm. Whitehall is a separate township from South Whitehall and North Whitehall. source |
| Allen Township | Northampton | In progress | May 7, 2026 | Supervisors began looking at adding data center as a defined zoning use, after approving the Prologis conversion. source |
| Lower Mount Bethel Township | Northampton | Adopted | September 14, 2026 | Supervisors voted unanimously to adopt Ordinance 2026-01, with guidelines on water, electricity and land use that a data center applicant must meet. source |
| Upper Mount Bethel Township | Northampton | In progress | September 21, 2026 | Supervisors voted 3 to 1 to send a township ordinance making data centers a conditional use in the I-2 and I-3 districts to the Lehigh Valley Planning Commission for review. Not yet final as far as we can confirm. A developer's validity challenge is pending. source |
Next step